|
Indoor Air Quality
Question: Does indoor air quality
mean that all buildings will be air conditioned? Will all rooms be
below 80 degrees Fahrenheit when the work is done?
Answer: Implicit in the bond planning
effort to address indoor air quality is the intent to control climate
and establish balanced temperatures throughout each facility. Climate
control implies that during warm or cold climates moisture levels
will be adjusted to inhibit contaminant growth. Drawing moisture out
of rooms during periods of warm climates will reduce temperature levels.
No specific temperature level has been established, however, the comfort
of individuals, as well as uniform and comfortable rooms throughout
each facility is the goal of the upcoming bond construction. Top
of Page
Question:Do air quality issues
make Pike Lake Elementary a top priority? Will air quality issues
be addressed at Highview Middle School?
Answer: Air quality issues and improvements
will be addressed at all District owned schools. As construction timelines
are established, those schools which have experienced significant
problems over recent years related to air quality problems, such as
Pike Lake Elementary, will have top priority. Top of
Page
Question: Have indoor air quality
standards been established? Are there construction standards for ventilation?
Will previous work done by the District Indoor Air Quality Committee
be used as part of standards development?
Answer: Indoor air quality standards
will be developed by the District Indoor Air Quality Committee based
on previous work done by the District Indoor Air Quality Committee,
recommendations made by the Institute for Environmental Assessment
(IEA), and standards established by the American Society of Heating,
Refrigeration and Air Conditioning Engineers (ASHRAE). Top
of Page
Question: How will the $16 million
designated for bond referendum indoor quality improvements be allocated
to buildings?
Answer: Bond money dedicated for
indoor air quality improvements will not be allocated to buildings.
Cost of improvements at each site will be dependent on many variables.
Improvements will be designed to provide equal conditions at all school
regardless of cost distributions. Top of Page
Construction Bidding
Question: Is there a bidding process
in place? Who will oversee the bidding process? What are bidding timelines?
Answer: Bidding is a formal process
mandated under federal and state law for contracting with construction
companies. The process includes the development of construction specifications,
public advertisement (legal newspaper) requesting bids, contractor
submission of sealed bids, formal opening of sealed bids and award
of contract to the lowest responsible bidder. Construction specifications
are developed by architectural firms which are approved by the School
Board prior to public advertisement. Subsequent to the opening of
sealed bids, the architects review contractor bids thoroughly and
make recommendations to the School Board for contract award. The process
of bidding, subsequent to the development of construction specifications,
can take anywhere from one to two months. Top of Page
Question: Will you consider union
contractors?
Answer: The District will consider
all contractors in the bid process. Federal and state law requires
contracts be awarded to the lowest responsible bidder. Responsible
bidders may, or may not, be employee union workers. However, in order
for contractors to be considered responsible they must have a track
record of performance on construction projects. The performance and
experience of these companies will be carefully considered by the
architects prior to recommendations for contract award. Top
of Page
Communications
Question: What is the District
web site address?
Answer: http://district.moundsview.k12.mn.us
Top of Page
Question: Will other media be used
to communicate information?
Answer: In addition to the internet,
communication will be provided through cable cast of School Board
meetings, School Talk newsletter (published quarterly in the Bulletin
newspapers), Community Education Brochure, school newsletters, employee
Grapevine newsletter, and periodic special mailings. Top
of Page
Construction Schedules
Question: What percent of construction
will be done during the school year calendar? Is it possible to change
the school calendar to accommodate building construction? Will construction
only occur during the summer?
Answer: Construction will take
place year-round. It would be impossible to complete $80 million in
construction projects over four to five years without year-round effort.
The percentage of construction that will occur during the school year
will be dependent on project scope at each site. School calendars
are controlled by state law, School Board policy, and collective bargaining
agreements and cannot be changed to reflect timing of construction
projects. Top of Page
Question: How will safety concerns
and extended day care issues during the construction process be addressed?
Answer: Safety will be the first
and most important consideration in preparation for construction.
Architects, construction managers, District staff, school planning
committees and the School Board will be involved in some capacity
to assure that all building inhabitants will be completely safe. Safety
concerns will extend to all programs that utilize the facilities including
the regular school day, extended day care, co-curricular programs,
community programs, etc. Top of Page
School Facility Planning
Committees
Question: Will students have a
voice in the facility planning process?
Answer: Senior high planning committees
have students participating in committee process. Top
of Page
Question: How will teachers' expectations
of bond construction planning be addressed at the schools, and will
there be special meetings?
Answer: The principal at each school
has full charge of the program planning elements of bond construction.
They will communicate with teachers, as well as other staff, to keep
them abreast/involved in the planning process. Top
of Page
Question: How long will committees
be part of the process?
Answer: Facility planning committees
will meet frequently during October, November and December 1999 through
the schematic design phases of planning. Subsequent to that effort
the committees will work less frequently at each site until the construction
is completed. That process may continue for four or five years.
Question: How will committee meetings
be scheduled?
Answer: Meetings will be scheduled
by the principal and architects. Top of Page
Question: How much decision making
will take place in the Facility Planning Committees?
Answer: Decision making by each
School Facility Planning Committee will focus on "Program Improvements"
while other committees will establish standards such as Indoor Air
Quality, Athletic Facilities, Deterioration, Technology, and Instruction/Academics.
Top of Page
Other Issues
Question: Will there be some crossover
of work being done among various planning committees?
Answer: There will be some limited
crossover of work. For example, the Athletic Facility Planning Committee
will establish standards for gymnasiums through schematic design phases,
then the School Facility Planning Committee (where a gym addition
will be located) will be involved in further decisions affecting the
gym i.e. entrances, storage, floor markings, lavatories, etc. Top
of Page
Question: Does planning include
improvements to interior classrooms that will increase classroom dimensions?
Answer: It may. Changes will be
determined by School Facility Planning Committees and will be dependent
on program dollar and structural limitations. Top of
Page
Question: Is Stahl Construction
(construction management firm) large enough to oversee construction
at all schools at the same time?
Answer: The company itself is large
enough to handle construction at all schools at the same time. However,
not all schools can be done at the same time. If all schools were
done at the same time many after-school, weekend and/or community
programs would have no location to function for the duration of construction
which will last 4-5 years. Top of Page
Question: How long until all projects
are complete?
Answer: It is estimated that all
projects will be completed in 4-5 years. Top of Page
Question: The bond was not specific.
How did building program lists get established?
Answer: The bond was specific. Significant
literature was shared throughout the community as to program improvements.
The program improvement lists were established through a number of
efforts including school committees and the District Facility Planning
Task Force prior to the bond referendum. Top of Page
Question: Can classrooms be moved
throughout the facility to minimize disruptions?
Answer: Yes. In fact, there will
likely be numerous times that classrooms and programs will undergo
temporary relocation within the site and possibly to other locations.
Top of Page
Question: Has the architectural
firm of Perkins & Will worked with school remodeling and program
relocation?
Answer: Yes. Both Perkins &
Will and ATS&R architectural firms have significant experience
working with schools facing similar levels of construction. Top
of Page
Question: Will architects plan
facility improvements to create a legacy for themselves?
Answer: No, for a number of reasons.
First, there are limits of dollars assigned to each building for program
improvements that must be addressed. Second, the District engaged
a construction management firm (Stahl Construction) to monitor the
planning process. Third, bond construction money will improve facilities
as described to voters in the Bond Referendum. Fourth, the Administration
and School Board will oversee program changes and facility improvements.
Top of Page
Question: Will specific staff from
the architectural firms be assigned to schools?
Answer: Yes. There may be support of other architectural staff within
each firm during the early planning phases of bond construction due
to the significant number of planning meetings that will take place.
Top of Page
Question: What might happen if
the school principal who has been involved in past planning departs?
Answer: Nothing will change. Program
improvements have been established. Each school has a planning committee
that will decide how those improvements are defined. The committees
will continue over the construction period and assure continuity of
plans. Top of Page
Question: Will the cities be involved
early in the planning process?
Answer: Yes. The cities are involved
with the Athletic Facility Planning Committee. Also, the District
will be working with each city building inspector and planning commission
before, during and after construction. Top of Page
Question: In what ways will technology
dollars be directed?
Answer: Some money is part of the
bond construction, primarily in areas affecting facility infrastructure
(wiring, network communications, etc.). There is also an amount of
money that is set aside in the Capital Expenditure budget (outside
of the bond) each year to replace aging equipment and increase the
numbers of computers available for use. The Technology Department
is developing plans for the deployment of both bond and capital expenditure
resources. Top of Page
Question: Could a feedback checklist
be created for each site so that individual sub contractors can be
evaluated?
Answer: Architects and construction
managers involved in the bond process will take responsibility for
recommending and contracting with only the most competent sub-contractors.
Top of Page
Question: How will school security
be addressed beyond changing of school entries?
Answer: Each School Facility Planning
Committee will work with architects in planning changes at their site.
Changes may include other security changes such as cameras, metal
detectors, monitors, etc.. Planning processes will be introduced to
Crime Prevention through Environmental Design (CPTED). CPTED emphasizes
three design approaches including natural access controls, natural
surveillance and territorial behavior. Top of Page
Question: Instead of repairing
and modifying facilities, what would it cost to level a facility and
replace it with modern up-to-date facilities?
Answer: Replacing all facilities
would cost several hundred million dollars. In addition, current new
school building construction requires increased land acreage that
is not available within the District boundaries. Top
of Page
Question: What is the expected
maximum age or usefulness of sites built in the 1950's?
Answer: If a facility is not improved,
the facility would likely depreciate over roughly fifty years. However,
if improvements are made to the infrastructure the facility can last
hundreds of years. Top of Page
|