Pike Lake
Elementary School |
![]() |
![]() |
![]() |
![]() |
| Jan.
4, 2001 New classroom furniture to be installed |
Jan. 4 , 2001 | Jan. 4 , 2001 | Jan. 4 , 2001 |
![]() |
![]() |
![]() |
![]() |
| Jan. 4 , 2001 | Dec. 1, 2000 | Dec. 1, 2000 | Dec. 1, 2000 |
![]() |
![]() |
![]() |
![]() |
| Dec. 1, 2000 | Nov.
1, 2000 New masonry walls near complete for new administration area |
Nov.
1, 2000 New masonry walls for music and band area in progress |
Nov.
1, 2000 Installation of new joists in progress for the IMC area |
|
|||||